Madison, WI Header
File #: 12014    Version: 1 Name: Improvements accepted for Water Main by Private Contract to serve: Cardinal Glenn, Phase 2A.
Type: Resolution Status: Passed
File created: 9/15/2008 In control: BOARD OF PUBLIC WORKS
On agenda: 10/28/2008 Final action: 10/28/2008
Enactment date: 11/7/2008 Enactment #: RES-08-00980
Title: Improvements accepted for Water Main by Private Contract to serve: Cardinal Glenn - Phase 2A. (9th AD)
Sponsors: BOARD OF PUBLIC WORKS
Fiscal Note
No Funds Required.
Title
Improvements accepted for Water Main by Private Contract to serve:  Cardinal Glenn - Phase 2A.  (9th AD)
Body
RESOLVED, that Water Main Installation improvements in Cardinal Glenn - Phase 2A, which have been completed, be and are hereby approved, and that the Water Utility General Manager be authorized to accept surety in the amount of $4,000 to expire not earlier than October 28, 2009 to ensure performance of the one-year guaranty period.