File #: 20196    Version: 1 Name: Improvements accepted for Bike Paths - 2007, Contract No. 5806.
Type: Resolution Status: Passed
File created: 10/11/2010 In control: BOARD OF PUBLIC WORKS
On agenda: 11/9/2010 Final action: 11/9/2010
Enactment date: 11/10/2010 Enactment #: RES-10-00893
Title: Improvements accepted for Bike Paths - 2007, Contract No. 5806.
Sponsors: BOARD OF PUBLIC WORKS
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58240-810375-00-53W0211          $383,808.22
Title
Improvements accepted for Bike Paths - 2007, Contract No. 5806.
Body
BE IT RESOLVED, that the improvements on Bike Paths - 2007 have been completed on 11/09/07 be and are hereby accepted.  
 
Original Contract Sum      $           348,024.00
(Based on Actual Units)      $           372,208.54
Net Change by Change Orders      $             15,919.68 or 4.57%
Liquidated Damages      $               4,320.00
Final Contract Amount      $           383,808.22