File #: 04653    Version: 1 Name: Accepting curb and gutter, sidewalk, and other public infrastructure improvements constructed by private contract for 625 North Segoe Road (Weston Place) PUD, Private Contract No.1988.
Type: Resolution Status: Passed
File created: 10/3/2006 In control: BOARD OF PUBLIC WORKS
On agenda: 10/17/2006 Final action: 10/17/2006
Enactment date: 10/18/2006 Enactment #: RES-06-00888
Title: Accepting curb and gutter, sidewalk, and other public infrastructure improvements constructed by private contract for 625 North Segoe Road (Weston Place) PUD, Private Contract No.1988. (11th AD)
Sponsors: Common Council By Request
Fiscal Note
Private Contract, No City Funds Required.
Title
Accepting curb and gutter, sidewalk, and other public infrastructure improvements constructed by private contract for 625 North Segoe Road (Weston Place) PUD, Private Contract No.1988. (11th AD)
Body
WHEREAS, Stevens Construction Corporation, has satisfactorily completed the installation of curb and gutter, sidewalk and other public infrastructure improvements on Segoe Road adjacent to the 625 North Segoe Road (Weston Place) PUD.
 
NOW, THEREFORE, BE IT RESOLVED, that said improvements be and are hereby accepted.  
 
BE IT FURTHER RESOLVED, that the one-year guarantee on said improvements shall have commenced on November 19, 2005.
 
 
Increase in street infrastructure value for Project No. 53B1988 $20,400.60 useful life of 40 years.