File #: 12850    Version: 1 Name: Change Order Nos. 4-7 to Contract No. 6103, Sidewalk & Curb & Gutter Citywide Installation and Repair - 2008, to Raymond P. Cattell, Inc. in the amounts of $12,690.00, $425.00, $5,238.00, and $13,070.16, respectively.
Type: Miscellaneous Status: Approved
File created: 11/21/2008 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 12/3/2008
Enactment date: Enactment #:
Title: Change Order Nos. 4-7 to Contract No. 6103, Sidewalk & Curb & Gutter Citywide Installation and Repair - 2008, to Raymond P. Cattell, Inc. in the amounts of $12,690.00, $425.00, $5,238.00, and $13,070.16, respectively.
Attachments: 1. co 4-7 - 6103.pdf

Title

Change Order Nos. 4-7 to Contract No. 6103, Sidewalk & Curb & Gutter Citywide Installation and Repair - 2008, to Raymond P. Cattell, Inc. in the amounts of $12,690.00, $425.00, $5,238.00, and $13,070.16, respectively.

Body

See attached.