File #: 08848    Version: 1 Name: Improvements Accepted Contract No. 5921, Olin Avenue Waste Transfer Station Reconstruction - 2006.
Type: Resolution Status: Passed
File created: 1/16/2008 In control: BOARD OF PUBLIC WORKS
On agenda: 2/5/2008 Final action: 2/5/2008
Enactment date: 2/8/2008 Enactment #: RES-08-00150
Title: Improvements Accepted Contract No. 5921, Olin Avenue Waste Transfer Station Reconstruction - 2006. (14th AD)
Sponsors: Common Council By Request
Fiscal Note
No funds required.  Project accounting in CB63-58401-810409.
Title
Improvements Accepted Contract No. 5921, Olin Avenue Waste Transfer Station Reconstruction - 2006.  (14th AD)
Body
BE IT RESOLVED, that the construction improvements on Olin Avenue Waste Transfer Station which have been completed on September 2007 be and are hereby accepted.  
 
Original Contract Sum                  $1,878,000.00
Final Contract Sum                       
(Based on Actual Units)                $--
Net Change by Change Orders    $106,665.75
Liquidated Damages                     $--
Final Contract Amount                  $1,984,665.75
 
Contractor: Tri-North Builders, Inc.