File #: 22298    Version: 1 Name: Improvements accepted for John Nolen Path Rehabilitation - 2010; John Nolen Drive Bridge Approaches - 2010, Contract No. 6279.
Type: Resolution Status: Passed
File created: 4/27/2011 In control: BOARD OF PUBLIC WORKS
On agenda: 5/17/2011 Final action: 5/17/2011
Enactment date: 5/23/2011 Enactment #: RES-11-00479
Title: Improvements accepted for John Nolen Path Rehabilitation - 2010; John Nolen Drive Bridge Approaches - 2010, Contract No. 6279.
Sponsors: BOARD OF PUBLIC WORKS
Title
Improvements accepted for John Nolen Path Rehabilitation - 2010; John Nolen Drive Bridge Approaches - 2010, Contract No. 6279.
Body
BE IT RESOLVED, that the improvements on John Nolen Path Rehabilitation - 2010; John Nolen Drive Bridge Approaches - 2010 have been completed on 7/03/10 be and are hereby accepted.  
 
Original Contract Sum         $            551,403.00
(Based on Actual Units)      $            505,671.79
Net Change by Change Orders      $             44,661.41 or 8.10%
Liquidated Damages      $                     0.00
Final Contract Amount      $           550,333.20
Fiscal Note
Breakdown of Costs by Account Number:
 
Acc't. No. CS53-54472-810358-00-53w0888        $295,802.90
Acc't. No. CS53-58270-810358-00-53w0888            $7,906.00
Acc't. No. CS53-58240-810375-00-53w0661         $246,624.30