Madison, WI Header
File #: 07077    Version: 1 Name: Accepting storm sewer constructed by private contract in Blackhawk Church Town Center Plat - Phase II, Private Contract No. 2071.
Type: Resolution Status: Passed
File created: 7/25/2007 In control: BOARD OF PUBLIC WORKS
On agenda: 9/4/2007 Final action: 9/4/2007
Enactment date: 9/7/2007 Enactment #: RES-07-00878
Title: Accepting storm sewer constructed by private contract in Blackhawk Church Town Center Plat - Phase II, Private Contract No. 2071. (9th AD)
Sponsors: Common Council By Request
Attachments: 1. stm-2071.pdf
Fiscal Note
This resolution increases the Total Plant Value for the Madison Storm Water Utility $50,285.53
Title
Accepting storm sewer constructed by private contract in Blackhawk Church Town Center Plat - Phase II, Private Contract No. 2071.  (9th AD)
Body
WHEREAS, Brader Way, LLC has satisfactorily completed the installation of storm sewer improvements by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in:
 
Blackhawk Church Town Center Plat - Phase II
 
NOW, THEREFORE, BE IT RESOLVED, that said storm sewer improvements be and are hereby accepted.
 
BE IT FURTHER RESOLVED, that said storm sewer improvements are hereby assigned to the Madison Storm Water  Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service".  
 
Increase in Total Plant Value per Schedule "A"  $50,285.53