Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58280-810376-00-53B0991 $86,001.61
Acc't. No. CS53-58250-810194-00-53B0201 $975.00
Acc't. No. ES01-58275-810054-00-53B0991 $2,741.78
Acc't. No. CW53-58270-810079-00-53B0991 $4,768.05
Acc't. No. EW01-58273-810455-00-53B0991 $137,060.46
Acc't. No. CP60-54301-810405-00-609805 $6,293.25
Acc't. No. CS53-58280-810068-00-53W0062 $8,572.88
Title
Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Concrete Curb & Gutter Installed at the Request of the Property Owner, Contract No. 5481. (Various ADs)
Body
BE IT RESOLVED, that the street, water main, and sanitary sewer improvements on Annual Construction & Reconstruction of Concrete Sidewalk & Concrete Curb & Gutter Installed at the Request of the Property Owner - 2003 have been completed on 1/29/05 be and are hereby accepted.
Original Contract Sum $ 152,922.50
(Based on Actual Units) $ 139,800.90
Net Change by Change Orders $ 106,612.13 or 69.72%
Liquidated Damages $ 0.00
Final Contract Amount $ 246,413.03