Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810041-00-53B0507 $44,859.92
Acc't. No. CW53-58270-810079-00-53B0507 $19,746.48
Title
Improvements accepted for Block 1 Alley Reconstruction District - 2002, Contract No. 5394. (13th AD)
Body
BE IT RESOLVED, that the sanitary sewer improvements on Block 1 Alley Reconstruction District - 2002 have been completed on 8/29/02 be and are hereby accepted.
Original Contract Sum $ 61,476.00
(Based on Actual Units) $ 56,700.72
Net Change by Change Orders $ 7,905.68 or 12.85%
Liquidated Damages $ 0.00
Final Contract Amount $ 64,606.40