Title:
|
Legistar 52062 - Recommended adoption at the June 20th BPW Meeting.
Note as requested by Rob for the removal of the bike/pedestrian path in 1000 Oaks - Phase 6, Contract 8198.
In 1000 Oaks Phase 6, contract 8198, the bike/pedestrian path along Crimson Leaf Lane and through the western portion of Outlot 3 will be eliminated due to design constraints related to pond grades. Standard sidewalk will be constructed on the west and east side of Crimson Leaf Lane from Watts Road to Sunny Spring Drive.
|