File #: 48294    Version: 1 Name: Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract in Hawks Valley - Phase 2, Private Contract No. 2401.
Type: Resolution Status: Passed
File created: 8/2/2017 In control: BOARD OF PUBLIC WORKS
On agenda: 9/5/2017 Final action: 9/5/2017
Enactment date: 9/8/2017 Enactment #: RES-17-00683
Title: Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract in Hawks Valley - Phase 2, Private Contract No. 2401.
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 2401 street excluding bituminous Schedule A.pdf, 2. 2401-Storm Schedule A Total Cost.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
9/5/20171 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
8/23/20171 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
8/3/20171 Engineering Division Refer  Action details Meeting details Not available

Fiscal Note

Private Contract, No City Funds Are Required.

Title

Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract in  Hawks Valley - Phase 2, Private Contract No. 2401.

Body

WHEREAS, Woods Road Investments, Inc. has satisfactorily completed the installation of storm sewer and street improvements (excluding bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: Hawks Valley - Phase 2.

 

 

NOW, THEREFORE, BE IT RESOLVED

 

1.  That said storm sewer and street improvements (excluding bituminous surface pavement) be and are hereby accepted. 

 

2. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service". 

 

 

Increase in Total Plant Value per Schedule “A”                     $137,212.90

 

 

3. That the street improvements, excluding the bituminous pavement, on the following streets be and are hereby accepted:

 

                     Ashworth Drive from the west line of Lot 38 to the east line of lot 37 (existing street)

                     Raptor Drive from the north line of lot 32 (existing street) to the south line of Lot 68

 

The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 53B2401  $ 113,459.92 for a useful life of 40 years.