Madison, WI Header
File #: 01455    Version: 1 Name: Improvements Accepted for Metro North Transfer Point Park and Ride Lot, Contract # 5633
Type: Resolution Status: Passed
File created: 6/13/2005 In control: BOARD OF PUBLIC WORKS
On agenda: 7/5/2005 Final action: 7/5/2005
Enactment date: 7/7/2005 Enactment #: RES-05-00589
Title: Improvements Accepted for Metro North Transfer Point Park and Ride Lot, Contract # 5633. (12th AD)
Sponsors: Common Council By Request
Fiscal Note
Breakdown of costs by account number
ET01-58201-502470-00-0000000-TR120002-WI030074 - $248,136.16
Title
Improvements Accepted for Metro North Transfer Point Park and Ride Lot, Contract # 5633. (12th AD)                                                                     
Body
On April 30, 2004, the City Engineer opened bids for the North Transfer Point Park and Ride Lot project for Metro.  On May 18, 2004 the Common Council adopted a resolution, awarding the contract to Parisi Construction Co., Inc.  On May 12, 2005, Parisi Construction Co., Inc. submitted an affidavit certifying that the prevailing wage requirements have been met and on June 6, 2005, Parisi Construction Co., Inc. submitted a Waiver of Construction Lien affidavit and its request for final payment.
 
BE IT RESOLVED, that the Park and Ride Lot improvements at Metro's North Transfer Point which have been completed on October 16, 2004 be and are hereby accepted.  
 
 
Original Contract Sum                  $250,215.00
Final Contract Sum
(Based on Actual Units)                  $250,791.16
Net Change by Change Orders            $  --
Liquidated Damages                  $    2,655.00
Final Contract Amount                  $248,136.16