Title
Improvements accepted for Gettle Avenue Lift Station Rehabilitation, Contract No. 6153.
Body
BE IT RESOLVED, that the improvements on Gettle Avenue Lift Station Rehabilitation have been completed on 6/26/09 be and are hereby accepted.
Original Contract Sum $ 615,570.00
(Based on Actual Units) $ 615,570.00
Net Change by Change Orders $ 14,973.78 or 2.43%
Liquidated Damages $ 0.00
Final Contract Amount $ 630,543.78
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. ES01-58275-810334-00-53W0407 $630,543.78