File #: 37708    Version: 1 Name: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Johns Street (Cottage Grove Road intersection).
Type: Resolution Status: Passed
File created: 3/18/2015 In control: BOARD OF PUBLIC WORKS
On agenda: 3/31/2015 Final action: 4/21/2015
Enactment date: 4/23/2015 Enactment #: RES-15-00355
Title: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Johns Street (Cottage Grove Road intersection).
Sponsors: David Ahrens
Attachments: 1. noise var notice_Johns.pdf, 2. 53W1792SAN-(U3)PnP.pdf
Fiscal Note
No fiscal note required.
Title
Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Johns Street (Cottage Grove Road intersection).
Body
PREAMBLE



The City of Madison plans to complete utility replacement with street resurfacing on Johns Street from Olbrich Avenue to Cottage Grove Road. Due to sewer main reconstruction requirements, City Engineering proposes to allow the Contractor to work between the hours of 7:00 PM to 7:00 AM. The work taking place on this project cannot be constructed between the hours of 7:00 AM and 7:00 PM because:

1. Sanitary sewer main replacement through the intersection of Cottage Grove Road at the Johns Street intersection is needed to take place outside of normal business operation to avoid traffic delays/closures.

2. Waste water sewer bypass pumping for sanitary sewer replacement will require pumping of waste water across the Cottage Grove Road intersection at Johns Street. This work will greatly impact daily traffic on Cottage Grove Road during normal work hours


The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:

1. Set up for waste water bypass pumping with Cottage Grove Road.

2. Replacement of sanitary sewer main with closure of one lane in each direction on Cottage
Grove Road.

3. Full closure of Cottage Grove Road for two (2) nights to complete sanitary sewer replacement,
and manhole replacement; first night for manhole replacement, second night for any
emergency work to be completed that was not finished within the first night.



The estimated Dates are as follows:

1. Waste water bypass pumping set up and replacement of sanitary sewer main and manhole -
late April.

These date ranges are approximate, and will be more clearly defined as the work areas are identified or as weather and unforeseen circumstances dictate.

Construction activities generally exceed the noise limits imposed by ...