Fiscal Note
Breakdown of costs by Acct. Nos:
Acc't. No. CS53-58240-810375-00-53B0981 $266,312.48
Acc't. No. CS53-58280-810373-00-53W0058 $20,869.04
Title
Improvements accepted for Bike Paths - 2004, Contract No. 5484. (Various ADs)
Body
BE IT RESOLVED, that the street improvements on Bike Paths - 2004 have been completed on 9/4/04 be and are hereby accepted.
Original Contract Sum $ 185,918.25
(Based on Actual Units) $ 195,998.75
Net Change by Change Orders $ 91,182.77 or 49.04%
Liquidated Damages $ 0.00
Final Contract Amount $ 287,181.52