Fiscal Note
Budget authority is available in the following Acct. Nos.:
CS53-58250-810571-00-53W1192-53TIF032 $409,000 “Major Street Projects”
CS53-58270-810571-00-53W1192-53TIF032 $35,000 “Major Street Projects”
ESTM-58270-810381-00-53W1192-53TIF032 $35,000 “Accompanying Storm”
ES01-58275-810332-00-53W1192 $78,000 ”Sewer with Recon. Streets”
CS53-58545-810571-00-53W1192 $218,000 “Major Street Projects “
EW01-58273-810455-00-53W1192 $115,000 “Water-Water Mains”
City Cost - $578,600
Total Cost - $890,000
Title
Approving Plans, Specifications, And Schedule Of Assessments For West Gorham Street, North Henry Street and North Frances Street Assessment District - 2012.
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of West Gorham Street, North Henry Street and North Frances Street Assessment District - 2012 pursuant to a resolution of the Common Council, RES-12-00050, ID 24858, adopted 1/17/2012, which resolution was adopted thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.
BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum of $578,600 of the entire cost of said improvement.
2. That for those eligible property owners requesting construction of a rain garden in the public right-of-way adjacent to their property shall execute the necessary waiver of special assessments on forms provided by the City Engineer;
3. That the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon each such parcel.
4. That the Common Council determines such special assessments to be reasonable.
5. That the work or improvement be carried out in accordance with the reports as finally approved.
6...