Fiscal Note
No City Funds required. Private Contract.
Title
Accepting bituminous surface pavement constructed by Private Contract in Village at Autumn Lake Phase 12 Surface Paving, Private Contract No. 9099 (District 17).
Body
WHEREAS, VAL, LLC has satisfactorily completed the installation bituminous surface pavement by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, for: Village at Autumn Lake Phase 12 Surface Paving.
NOW, THEREFORE, BE IT RESOLVED
That the bituminous surface street improvements on the following streets be and are hereby accepted:
• Autumn Lake Parkway from 159 FT NE of Tori Frost Drive to Sanctuary Drive.
• Autumn Lake Parkway from Sanctuary Drive to E of Lot 1184.
• Sanctuary Drive from Autumn Lake Parkway to Spring Dreams Lane.
• Sanctuary Drive from Spring Dreams Lane to Waterfall Way.
• Sanctuary Drive from Waterfall Way to Felland Road.
• Waterfall Way from Sanctuary Drive to 295 FT N of Sanctuary Drive.
• Waterfall Way from E of Lot 1205 to Sanctuary Drive.
The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 13856 by $42,959.26 for a useful life of 40 years.