Fiscal Note
No funds required.
Title
Approving plans and specifications for the intersection of Cottage Grove Road/Dempsey Road and Dempsey Road between Cottage Grove Road and the Capital City Path.
Body
PREAMBLE
Cottage Grove Road between Monona Drive and Claire Street will be reconstructed in 2016. City Engineering and Traffic Engineering are proposing to install a diagonal bike crossing at the signalized intersection (see attached diagram). The diagonal crossing will provide bicyclists with a one stage crossing of the signalized intersection. Dempsey Road will also include a northbound on-street bike lane.
Construction and funding will be included with project 10250, Cottage Grove Road and Dempsey Road Street Assessment District-2016, File ID 40938.
NOW THEREFORE BE IT RESOLVED that the plans and specifications for the intersection of Cottage Grove Road/Dempsey Road and Dempsey Road between Cottage Grove Road and the Capital City Path, is hereby approved.