Madison, WI Header
File #: 22736    Version: 1 Name: Approving final plans for the installation of speed humps on Allied Drive and Jenewein Road.
Type: Resolution Status: Passed
File created: 6/7/2011 In control: BOARD OF PUBLIC WORKS
On agenda: 6/21/2011 Final action: 6/21/2011
Enactment date: 6/22/2011 Enactment #: RES-11-00561
Title: Approving final plans for the installation of speed humps on Allied Drive and Jenewein Road (10th AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. cp2011_Allied-2400_Humps.pdf
Fiscal Note
Estimated cost: $22,000
Budget authority is available in CS53-54472-810360-00-53W1143 "Neighborhood Traffic Mgmt"
 
Title
Approving final plans for the installation of speed humps on Allied Drive and Jenewein Road (10th AD)
 
Body
PREAMBLE
This project consists of installation of three speed humps on Allied Drive and one speed hump on Jenewein Road
Construction is scheduled for 2011 and will be accomplished with the Local Road Traffic Calming & Arterial Ped Enhancements-2011 public works contract.  
 
BE IT RESOLVED that the final plans for the installation of speed humps on Allied Drive and Jenewein Road, be and are hereby approved.