Madison, WI Header
File #: 05528    Version: 1 Name: Accepting bituminous pavement constructed by private contract in Ridgewood The Glacier Addition, Phase VI, Private Contract No. 1851.
Type: Resolution Status: Passed
File created: 1/30/2007 In control: BOARD OF PUBLIC WORKS
On agenda: 2/27/2007 Final action: 2/27/2007
Enactment date: 2/28/2007 Enactment #: RES-07-00249
Title: Accepting bituminous pavement constructed by private contract in Ridgewood The Glacier Addition, Phase VI, Private Contract No. 1851. (17th AD)
Sponsors: Common Council By Request

Fiscal Note

Private Contract. No City Funds Are Required.

Title

Accepting bituminous pavement constructed by private contract in Ridgewood The Glacier Addition, Phase VI, Private Contract No. 1851. (17th AD)

Body

WHEREAS, Don Simon Homes, Inc. has satisfactorily completed the installation of bituminous pavement on the streets listed below by private contract in accordance with the City of Madison Standard Specifications for Public Works Construction. 

 

NOW, THEREFORE, BE IT RESOLVED, that the bituminous pavement on the following streets be and is hereby accepted:

 

Madison Standard Street Improvements, including sidewalk:

 

- Hazelcrest Drive from the west line of Lot 128 (existing street) to the east line of Lot 27 (existing street)

- Vernon Road from Hazelcrest Drive to the south plat line (including a type A bituminous transition to the existing roadway).

 

Increase in street infrastructure value for Project No. 53B1851 $7,625.00 useful of 40 years. 

 

BE IT FURTHER RESOLVED, that the one year warranty shall have commenced December 15, 2004.