Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53B0686 $362,747.86
Acc't. No. ESTM-58270-810381-00-53B0686 $182,836.52
Acc't. No. EW01-58275-810455-00-53B0686 (#7217) $324,559.93
Acc't. No. ES01-58275-810332-00-53B0686 $281,918.99
Title
Improvements accepted for Campbell Street, Chandler Street, Garfield Street and Vilas Avenue Reconstruction Assessment District - 2004, Contract No. 5603. (13th AD)
Body
BE IT RESOLVED, that the street, water main and storm and sanitary sewer improvements on Campbell Street, Chandler Street, Garfield Street and Vilas Avenue Reconstruction Assessment District - 2004 have been completed on 8/6/05 be and are hereby accepted.
Original Contract Sum $ 1,310,874.10
(Based on Actual Units) $ 1,152,332.59
Net Change by Change Orders $ 6,660.71 or 0.50%
Liquidated Damages $ 6,930.00
Final Contract Amount $ 1,152,063.30