Madison, WI Header
File #: 15777    Version: 1 Name: Improvements Accepted for James Madison Park Basketball Court and Parking Lot ~ Contract #6267
Type: Resolution Status: Passed
File created: 8/24/2009 In control: BOARD OF PUBLIC WORKS
On agenda: 9/15/2009 Final action: 9/15/2009
Enactment date: 9/16/2009 Enactment #: RES-09-00799
Title: Improvements Accepted for James Madison Park Basketball Court and Parking Lot ~ Contract #6267 (AD #2)
Sponsors: Bridget R. Maniaci, Joseph R. Clausius, Paul E. Skidmore
Fiscal Note
Breakdown of Costs by Account Number as shown below:
Title
Improvements Accepted for James Madison Park Basketball Court and Parking Lot ~  Contract #6267 (AD #2)
Body
 
BE IT RESOLVED, That the basketball court and parking lot improvements at James Madison Park have been completed on August 20, 2009 and they be and are hereby accepted.
 
Original Contract Sum                  $  139,711.60
(Based on Actual Units)
Net Change by Change Orders            $        -0-
Liquidated Damages
Final Contract Amount                  $  139,711.60
 
 
Account Number                                    Amount
CL60-58201-810579-00-0000000-60000A00            $139,711.60