Fiscal Note
In the adopted 2016 capital budget the Water Utility has budgeted $6.2 million for the Paterson Street Operations Center Remodel (MUNIS 12095). The minor project for the SCADA room renovation is established with sufficient authority for the estimated cost of the project. Funding is provided by revenue bonds.
The proposed resolution approves the contract for the work at an estimated cost of $67,850.00
MUNIS:
12095-86-140 - $67,850.00
Title
Awarding Public Works Contract No. 7735, Madison Water Utility - SCADA Room Renovation 119 E Olin Ave.
Body
BE IT RESOLVED, that the following low bids for miscellaneous improvements be accepted and that the Mayor and City Clerk be and are hereby authorized and directed to enter into a contract with the low bidders contained herein, subject to the Contractor's compliance with Section 39.02 of the Madison General Ordinances concerning compliance with the Affirmative Action provisions and subject to the Contractor's compliance with Section 33.07 of the Madison General Ordinances regarding Best Value Contracting:
BE IT FURTHER RESOLVED, that the funds be encumbered to cover the cost of the projects contained herein.
See attached document (Contract No. 7735) for itemization of bids.