File #: 13480    Version: 1 Name: Change Order No. 11 to Contract No. 6019, E. Mifflin and N. Blount Street Street Reconstruction to Parisi Construction in the amount of $19,800.00 with a contract time increase of 21-days.
Type: Miscellaneous Status: Approved
File created: 1/27/2009 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 2/4/2009
Enactment date: Enactment #:
Title: Change Order No. 11 to Contract No. 6019, E. Mifflin and N. Blount Street Street Reconstruction to Parisi Construction in the amount of $19,800.00 with a contract time increase of 21-days.
Attachments: 1. co 11 - 6019.pdf

Title

Change Order No. 11 to Contract No. 6019, E. Mifflin  and N. Blount Street Street Reconstruction to Parisi Construction in the amount of $19,800.00 with a contract time increase of 21-days. 

Body

See attached.