Fiscal Note
Funds available in accounts as listed below.
These costs are to be charged against the following Account Number:
CL60-58201-810396-00-6090032-60244S04 $27,573.30
Title
Improvements accepted for Thai Pavilion Pathways, Contract No. 5641. 6th & 15th Ald. Districts.
Body
BE IT RESOLVED, that the Thai Pavalion Pathways improvement in Olbrich Botanical Gardens has been completed, and are hereby accepted.
Original Contract Sum $ 27,573.30
Final Contract Sum $ 27,573.30
(Based on Actual Units)
Net Change by Change Orders $ N/A
Liquidated Damages $ N/A
Final Contract Amount $ 27,573.30