File #: 14698    Version: 1 Name: Improvements accepted for University/Highland Intersection Flooding, Contract No. 5991.
Type: Resolution Status: Passed
File created: 5/11/2009 In control: BOARD OF PUBLIC WORKS
On agenda: 6/2/2009 Final action: 6/2/2009
Enactment date: 6/5/2009 Enactment #: RES-09-00525
Title: Improvements accepted for University/Highland Intersection Flooding, Contract No. 5991.
Sponsors: BOARD OF PUBLIC WORKS
Title
Improvements accepted for University/Highland Intersection Flooding, Contract No. 5991.
Body
 
BE IT RESOLVED, that the improvements on University/Highland Intersection Flooding have been completed on 7/21/07 be and are hereby accepted.  
 
Original Contract Sum      $         206,214.50
(Based on Actual Units)      $         206,462.54
Net Change by Change Orders      $           12,211.50 or 5.92%
Liquidated Damages      $                   0.00
Final Contract Amount      $         218,674.04
 
 
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. ESTM-58270-810514-00-53W0371        $218,674.04