Improvements accepted for University/Highland Intersection Flooding, Contract No. 5991.
Body
BE IT RESOLVED, that the improvements on University/Highland Intersection Flooding have been completed on 7/21/07 be and are hereby accepted.
Original Contract Sum $ 206,214.50
(Based on Actual Units) $ 206,462.54
Net Change by Change Orders $ 12,211.50 or 5.92%
Liquidated Damages $ 0.00
Final Contract Amount $ 218,674.04
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. ESTM-58270-810514-00-53W0371 $218,674.04