Madison, WI Header
File #: 80819    Version: 1 Name: Change order No. 1 to Contract 9226, Phase 2 CCB Office REmodels 1st and 5th Floors, to Tri-North Builders Inc for $102,328.84 and a completion date of January 29, 2024.
Type: Miscellaneous Status: Approved
File created: 11/13/2023 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 11/20/2023
Enactment date: Enactment #:
Title: Change order No. 1 to Contract 9226, Phase 2 CCB Office REmodels 1st and 5th Floors, to Tri-North Builders Inc for $102,328.84 and a completion date of January 29, 2024. (District 4)
Attachments: 1. 9226 co 1.pdf

Title

Change order No. 1 to Contract 9226, Phase 2 CCB Office REmodels 1st and 5th Floors, to Tri-North Builders Inc for $102,328.84 and a completion date of January 29, 2024. (District 4)

Body

See attached