File #: 15682    Version: 1 Name: Change Order No. 1 to Contract No. 6233, Allis Avenue Water Main Replacement Project, to Speedway Sand & Gravel, in the amount of $65,709.37.
Type: Miscellaneous Status: Approved
File created: 8/12/2009 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 8/19/2009
Enactment date: Enactment #:
Title: Change Order No. 1 to Contract No. 6233, Allis Avenue Water Main Replacement Project, to Speedway Sand & Gravel, in the amount of $65,709.37.
Attachments: 1. co 1 - 6233.pdf

Title

Change Order No. 1 to Contract No. 6233, Allis Avenue Water Main Replacement Project, to Speedway Sand & Gravel, in the amount of $65,709.37.

Body

See attached.