File #: 12466    Version: 1 Name: Improvements accepted for Cottage Grove Road Bike Lanes - 2006, Contract No. 5613.
Type: Resolution Status: Passed
File created: 10/28/2008 In control: BOARD OF PUBLIC WORKS
On agenda: 12/2/2008 Final action: 12/2/2008
Enactment date: 12/8/2008 Enactment #: RES-08-01081
Title: Improvements accepted for Cottage Grove Road Bike Lanes - 2006, Contract No. 5613.
Sponsors: BOARD OF PUBLIC WORKS
Title
Improvements accepted for Cottage Grove Road Bike Lanes - 2006, Contract No. 5613.
Body
BE IT RESOLVED, that the improvements on Cottage Grove Road Bike Lanes - 2006 have been completed on 6/23/07 be and are hereby accepted.  
 
Original Contract Sum      $         305,304.80
(Based on Actual Units)      $         321,539.22
Net Change by Change Orders      $             3,750.00 or 1.22%
Liquidated Damages      $                   0.00
Final Contract Amount      $         325,289.22
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810359-00-53W0057        $151,949.29
Acc't. No. CS53-58250-810301-00-53W0057        $131,760.00
Acc't. No. CS53-58270-810301-00-53W0057          $17,300.00
Acc't. No. CS53-58545-810301-00-53W0057          $24,279.93