Fiscal Note
Breakdown of Costs by Account Number as shown below:
Title
Improvements Accepted for Cypress Spray Park Contract #5980 (14th AD)
Body
BE IT RESOLVED, That the construction of the Cpyress sprayground and dry playground in the city have been completed on December 14, 2007 be and are hereby accepted.
Original Contract Sum $ 375,505.50
(Based on Actual Units)
Net Change by Change Orders $ 14,895.15
Liquidated Damages
Final Contract Amount $ 390,400.65
Account Number Amount
CL60-58201-810582-00-0000000-60229S00 $ 390,400.65