Madison, WI Header
File #: 34816    Version: Name: 10409 TLE Lakeview Water Tower demolition and reconstruction project
Type: Resolution Status: Passed
File created: 7/9/2014 In control: WATER UTILITY BOARD
On agenda: 8/5/2014 Final action: 8/5/2014
Enactment date: 8/7/2014 Enactment #: RES-14-00617
Title: SUBSTITUTE: Authorizing the execution of a temporary limited easement agreement with the County of Dane for construction access and staging purposes during the City’s Lakeview Water Tower demolition and reconstruction project.
Sponsors: Lauren Cnare, Anita Weier
Attachments: 1. 10409 Exhibit.pdf, 2. File 34816 Version 1.pdf
Fiscal Note
Any costs associated with the temporary limited easement agreement are included in Water Utility Capital Budget Account EW01-58310-810458.
Title
SUBSTITUTE: Authorizing the execution of a temporary limited easement agreement with the County of Dane for construction access and staging purposes during the City’s Lakeview Water Tower demolition and reconstruction project.
Body
WHEREAS, the City of Madison and the County of Dane are parties to an easement agreement dated November 18, 1997 (the “Easement”) which provides the City with a perpetual, exclusive easement over a portion of the County-owned property located at 1202 Northport Drive (the “Tower Easement Area”) for the operation of the City-owned Lakeview Water Tower (the “Existing Water Tower”); and

WHEREAS, the Easement also provides the City with a perpetual non-exclusive easement over a portion of the County-owned property for purposes of pedestrian and vehicular ingress and egress to and from the Tower Easement Area (the “Ingress/Egress Easement”); and

WHEREAS, the Tower Easement Area and the Ingress/Egress Easement Area are depicted on attached Exhibit A; and

WHEREAS, as allowed under the terms of the Easement, the City has licensed space on the Existing Water Tower and within the Tower Easement Area to three (3) telecommunication companies for the installation and operation of telecommunications equipment and improvements; and

WHEREAS, during 2014 and 2015 the City will be engaged in a project (the “Project”) involving the demolition of the Existing Water Tower and the construction of a new tower in its place (the “New Water Tower”); and

WHEREAS, during such Project, the City is requiring that all telecommunication and radio equipment be removed from the Existing Water Tower and relocated onto a temporary monopole to be erected by the telecommunication companies within the Tower Easement Area (the “Temporary Monopole”); and

WHEREAS, the City, its authorized agents, contractors and ...

Click here for full text