Fiscal Note
General Obligation Debt: |
$113,000 |
Other Funding: |
$0 |
Total: |
$113,000 |
Debt Service: |
$13,247 |
TOAH Impact: |
$0.15 |
Title
CAPITAL BUDGET AMENDMENT # 3 - Facilities Management / Air Conditioning Units - IT Server (New), p. 42
Body
The Information Technology Data Center renovation is an approved project in the 2011 Facilities Management capital budget. This project will replace old air conditioning systems with more energy efficient ones resulting in long term cost savings and continued reliable computer operations. Bids came in higher than expected and an additional $113,000 is needed to complete the project.