File #: 11521    Version: 1 Name: Change Order No. 10 to Contract No. 6080, CCB/MMB Tenant Improvement Remodels - Phase 2, to Miron Construction Co., Inc. in the amount of $21,147.00 with a contract time increase of 64-days.
Type: Miscellaneous Status: Approved
File created: 7/31/2008 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 8/6/2008
Enactment date: Enactment #:
Title: Change Order No. 10 to Contract No. 6080, CCB/MMB Tenant Improvement Remodels - Phase 2, to Miron Construction Co., Inc. in the amount of $21,147.00 with a contract time increase of 64-days.
Attachments: 1. pictures.pdf, 2. diagram.pdf

Title

Change Order No. 10 to Contract No. 6080, CCB/MMB Tenant Improvement Remodels - Phase 2, to Miron Construction Co., Inc. in the amount of $21,147.00 with a contract time increase of 64-days.