File #: 11103    Version: 1 Name: Change Order No. 9 to Contract No. 6080, CCB/MMB Tenant Improvement Remodels - Phase 2, to Miron Construction Co., Inc. in the amount of $6,408.00 with an increase of 14-days of contract time.
Type: Miscellaneous Status: Approved
File created: 7/9/2008 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 7/16/2008
Enactment date: Enactment #:
Title: Change Order No. 9 to Contract No. 6080, CCB/MMB Tenant Improvement Remodels - Phase 2, to Miron Construction Co., Inc. in the amount of $6,408.00 with an increase of 14-days of contract time.
Attachments: 1. co 9 - 6080.pdf

Title

Change Order No. 9 to Contract No. 6080, CCB/MMB Tenant Improvement Remodels - Phase 2, to Miron Construction Co., Inc. in the amount of $6,408.00 with an increase of 14-days of contract time.

Body

See attached.