Madison, WI Header
File #: 48307    Version: 1 Name: Accepting bituminous surface pavement constructed by Private Contract in Linden Park Phase 6, Private Contract No. 2204.
Type: Resolution Status: Passed
File created: 8/3/2017 In control: BOARD OF PUBLIC WORKS
On agenda: 9/5/2017 Final action: 9/5/2017
Enactment date: 9/8/2017 Enactment #: RES-17-00689
Title: Accepting bituminous surface pavement constructed by Private Contract in Linden Park Phase 6, Private Contract No. 2204.
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 2204 bituminous Schedule A.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
9/5/20171 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
8/23/20171 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
8/4/20171 Engineering Division Refer  Action details Meeting details Not available

Fiscal Note

Private Contract, No City Funds Are Required.

Title

Accepting bituminous surface pavement constructed by Private Contract in Linden Park Phase 6, Private Contract No. 2204.

Body

 

WHEREAS, Great Neighborhoods West, LLC % Veridian has satisfactorily completed the installation bituminous surface pavement by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, for:  Linden Park - Phase 6.

 

 

NOW, THEREFORE, BE IT RESOLVED

 

 

That the bituminous surface street improvements on the following streets be and are hereby accepted:

 

 

                     Winter Frost Place from the west plat line (west line of OL 25 (existing street) to Redan Drive (existing street).

                     Moonlight Trail from Winter Frost Place to the north line of Lot 263.

                     Ancient Oak Lane from Redan Drive (existing street) to the west line of Lot 280.

                     Redan Drive from Ancient Oak Lane (existing street) to the north line of Lot 282.

                     Shining Rock Trail from Ancient Oak Lane (existing street) to the north line of Lot 292.

                     Rung Way from Ancient Oak Lane (existing street) to the north line of Lot 302.

                     Reflection Drive from Ancient Oak Lane (existing street) to the north line of Lot 317.

 

The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 53B2204 by $13,659.40 for a useful life of 40 years.