File #: 36254    Version: 1 Name: Accepting bituminous surface improvements constructed by Private Contract In The Meadowlands -Phase 4, Private Contract No. 2083.
Type: Resolution Status: Passed
File created: 11/17/2014 In control: BOARD OF PUBLIC WORKS
On agenda: 12/2/2014 Final action: 12/2/2014
Enactment date: 12/3/2014 Enactment #: RES-14-00904
Title: Accepting bituminous surface improvements constructed by Private Contract In The Meadowlands -Phase 4, Private Contract No. 2083.
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 2083 bituminous Schedule A.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
12/2/20141 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
11/19/20141 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
11/17/20141 Engineering Division Refer  Action details Meeting details Not available
Fiscal Note
Private Contract, No City Funds Are Required.
Title
Accepting bituminous surface improvements constructed by Private Contract In The Meadowlands -Phase 4, Private Contract No. 2083.
Body
WHEREAS, Meadowlands Land, LLC has satisfactorily completed the installation of bituminous surface improvements by private contract in accordance with the City of Madison Standard Specifications for Public Works Construction for: The Meadowlands - Phase 4.
 
NOW, THEREFORE, BE IT RESOLVED
 
1. That the bituminous surface improvements on the following streets be and are hereby accepted:
 
·      Reston Heights Drive from the westerly line of Lot 69 (existing street) to the easterly line of Lot 112.
·      Golden Maple Road from The northerly line of Outlot 13 (existing street) to the southerly line of Lot 69 (existing street).
·      Shady Leaf Road from Reston Heights Drive to Littlemore Drive.
·      Littlemore Drive from the westerly line of Lot 75 (existing street) to the easterly line of Lot 99
·      Alley (Outlot 12) from Golden Maple Drive to Reston Heights Drive.
·      Alley (Outlot 13) from Golden Maple Road to the west line of Lot 208.
·      Alley (Outlot 1) from the westerly line of Lot 85 to Shady Leaf Road, and from the westerly line of Lot 78 to Shady Leaf Road.
·      Alley (Outlot 2) from the westerly line of Lot 113 at Shady Leaf Road to the westerly line of Lot 121 at Shady Leaf Road.
 
 
The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 53B2083  $36,279.02 for a useful life of 40 years.