Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 3 & 16) by the Common Council, Contract No. 6100.
Body
BE IT RESOLVED, that the improvements on Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 3 & 16) by the Common Council have been completed on 11/22/08 be and are hereby accepted.
Original Contract Sum $ 607,450.00
(Based on Actual Units) $ 569,105.46
Net Change by Change Orders $ 126,715.57 or 20.86%
Liquidated Damages $ 0.00
Final Contract Amount $ 695,821.03
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-54473-810376-00-53W0525 $687,271.78