File #: 14711    Version: 1 Name: Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 3 & 16) by the Common Council, Contract No. 6100.
Type: Resolution Status: Passed
File created: 5/11/2009 In control: BOARD OF PUBLIC WORKS
On agenda: 6/2/2009 Final action: 6/2/2009
Enactment date: 6/5/2009 Enactment #: RES-09-00532
Title: Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 3 & 16) by the Common Council, Contract No. 6100.
Sponsors: BOARD OF PUBLIC WORKS
Title
Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 3 & 16) by the Common Council, Contract No.  6100.
Body
BE IT RESOLVED, that the improvements on Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 3 & 16) by the Common Council have been completed on 11/22/08 be and are hereby accepted.  
 
Original Contract Sum      $         607,450.00
(Based on Actual Units)      $         569,105.46
Net Change by Change Orders      $         126,715.57 or 20.86%
Liquidated Damages      $                   0.00
Final Contract Amount      $         695,821.03
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-54473-810376-00-53W0525           $687,271.78
Acc't. No. CS53-58280-810376-00-53W0525               $8,549.25