Madison, WI Header
File #: 05110    Version: 1 Name: Accepting street improvements constructed by private contract in Grandview Commons Phase VI, Private Contract No. 1920.
Type: Resolution Status: Passed
File created: 11/30/2006 In control: BOARD OF PUBLIC WORKS
On agenda: 1/2/2007 Final action: 1/2/2007
Enactment date: 1/3/2007 Enactment #: RES-07-00022
Title: Accepting street improvements constructed by private contract in Grandview Commons Phase VI, Private Contract No. 1920. (3rd AD)
Sponsors: Common Council By Request
Fiscal Note
Private Contract. No City Funds Are Required.
Title
Accepting street improvements constructed by private contract in Grandview Commons Phase VI, Private Contract No. 1920. (3rd AD)
Body
WHEREAS, Premium Real Estate, LLC   c/o  Veridian Homes, has satisfactorily completed the installation of street improvements on the streets listed below by private contract in accordance with the City of Madison Standard Specifications for Public Works Construction.  
 
NOW, THEREFORE, BE IT RESOLVED, that the following streets be and are hereby accepted:
 
Hercules Trail from Halley Way (existing street) to the north line of Lot 473.
Halley Way from Juniper Drive to Hercules Trail.
Juniper Drive from the south line of Lot 463 (existing street) to the north line of Lot 463.
Public alley in Outlot 29.  
 
Increase in street infrastructure value for Project No. 53B1920 $167,142.00 useful life of 40 years.  
 
BE IT FURTHER RESOLVED, that the one-year guarantee shall have commenced on December 7, 2005.