Fiscal Note
Breakdown of costs by Acct. No. Acc't. No. CS53-58280-810376-00-53B0990 $864,071.91
Title
Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 5) by the Common Council, Contract No. 5479. (5th AD)
Body
BE IT RESOLVED, that the street improvements on Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 5) by the Common Council have been completed on 6/3/04 be and are hereby accepted.
Original Contract Sum $ 499,645.00
(Based on Actual Units) $ 539,792.97
Net Change by Change Orders $ 324,278.94 or 64.90%
Liquidated Damages $ 0.00
Final Contract Amount $ 864,071.91