File #: 43727    Version: 1 Name: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM for work associated with City of Madison cured in place lining, Contract No. 7756 (Project No. #10290).
Type: Resolution Status: Passed
File created: 7/13/2016 In control: BOARD OF PUBLIC WORKS
On agenda: 7/19/2016 Final action: 9/6/2016
Enactment date: 9/9/2016 Enactment #: RES-16-00622
Title: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM for work associated with City of Madison cured in place lining, Contract No. 7756 (Project No. #10290).
Sponsors: Ledell Zellers
Attachments: 1. Noise Impact Public Hearing Notice.pdf
Fiscal Note
No Funds Required.
Title
Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM for work associated with City of Madison cured in place lining, Contract No. 7756 (Project No. #10290).
Body

The City of Madison large diameter cured in place pipe (CIPP) project intends to rehabilitate approximately 7,500 linear feet of 24” and 30” diameter sanitary and storm sewer located on E. Washington Ave, Blair St, Railroad St, Blount St, N. Midvale Ave, and Tenney Park Locks. The curing method associated with this project does not allow for all construction activities of the project to take place during the normal working hours of 7:00AM and 7:00PM.

Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities outside of the hours of 7:00 AM to 7:00 PM with the passage of a resolution and a hearing before the Board of Public Works. It is anticipated that the Contractor performing this work will call for permission to perform the work required to cure in place line segments of sanitary sewer interceptors on Randall Ave, Regent St, E. Washington Ave, Blair St, Railroad St, and Blount St outside the hours of 7:00 AM to 7:00 PM because:

1. The section of sanitary sewer main to be lined has high flow during the hours of 7:00 AM to 7:00 PM.
2. The streets where this work is scheduled to occur convey high volumes of traffic. Activities associated with lining these sanitary mains will disrupt live traffic causing considerable disruption and delay.
3. The CIPP process may exceed the twelve (12) hour window provided by the General Ordinance.

The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:

1. Hydraulic cleaning of the sanitary sewer main sections to be lined to remove any accumulated debris prior to lining;
2. Conducting a closed-circuit inspection of the sanitary sewer mains to be lined to confirm that the line has been ade...

Click here for full text