Madison, WI Header
File #: 28936    Version: Name: SUBSTITUTE Approving plans & specifications for the proposed improvements & authorizing the Mayor & City Clerk to execute agreements with the State of Wisconsin DOT for the local road, sanitary sewer, water main & community sensitive design construction
Type: Resolution Status: Passed
File created: 1/28/2013 In control: BOARD OF PUBLIC WORKS
On agenda: 2/26/2013 Final action: 2/26/2013
Enactment date: 2/28/2013 Enactment #: RES-13-00128
Title: SUBSTITUTE Approving plans and specifications for the proposed improvements and authorizing the Mayor and City Clerk to execute agreements with the State of Wisconsin Department of Transportation for the local road, sanitary sewer, water main and community sensitive design construction of the Verona Road & Seminole Highway Project.
Sponsors: Matthew J. Phair
Attachments: 1. Verona Rd overall plan.pdf, 2. Verona Rd landscaping plan.pdf, 3. roundabout bridge.pdf, 4. Beltline Bridge.pdf, 5. whitney gilbert int.pdf, 6. seminole nakoma int.pdf, 7. Seminole Path.pdf, 8. w beltline path.pdf, 9. Water Main Staging.pdf, 10. 101612 Sewer Overview.pdf, 11. NAKOMA SEMINOLE INTERSECTION SEWER WORK(traffic signal conflict).pdf, 12. version 1 - 28936.pdf
Fiscal Note
Budget authority is available in the following Acct. Nos.:
Sanitary Sewer Acct. No. ES01-58275-810332-00-53W0904 $974,540 $1,170,000.00
Water Acct. No. EW01-58273-810455-00-53W0904 $1,307,770 $1,680,000.00
Total Cost: $94,629,310 $95,880,000.00
Federal Share: $92,347,000 $93,030,000.00
City Share: $2,282,310 $2,850,000.00
Construction is planned for 2013-2016 and therefore will primarily be funded by future Capital Budgets.

Title
SUBSTITUTE Approving plans and specifications for the proposed improvements and authorizing the Mayor and City Clerk to execute agreements with the State of Wisconsin Department of Transportation for the local road, sanitary sewer, water main and community sensitive design construction of the Verona Road & Seminole Highway Project.
Body
PREAMBLE
The State of Wisconsin Department of Transportation (WisDOT) is proposing improvements to Verona Road (Nakoma Road to Raymond Road), USH 12, (Whitney Way to Seminole Highway) and Seminole Highway (Overpass of USH 12). Construction will also include work along frontage roads of Verona Road and USH 12 which are local City of Madison streets.
The project will be constructed under a contract let by the Wisconsin Department of Transportation (WisDOT) and a project Agreement with WisDOT will be required for funding, oversight and construction. The proposed project is planned for construction in the year 2013-16.

The work includes improvements to the following roadways: Frontage Roads of USH 12, Frontage Roads of Verona Road, Allied Drive, West Beltine Bike Path, Seminole/Arboretum Bike Path, Whitney Way/Gilbert Road intersection and Nakoma Road/Seminole Highway intersection. The work also includes improvements for storm sewer, sanitary sewer and water main for the above referenced roadways.

The City of Madison and the WisDOT propose to enter into an agreement for construction and cost sharing of the proposed project. The basis for cost sharing participatio...

Click here for full text