File #: 05404    Version: 1 Name: Improvements accepted for TANCHO/CIC Phase II Construction, Contract No. 5852.
Type: Resolution Status: Passed
File created: 1/11/2007 In control: BOARD OF PUBLIC WORKS
On agenda: 2/6/2007 Final action: 2/6/2007
Enactment date: 2/7/2007 Enactment #: RES-07-00177
Title: Improvements accepted for TANCHO/CIC Phase II Construction, Contract No. 5852. (17th AD)
Sponsors: Common Council By Request
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810438-00-53W0257    $91,671.35
Title
Improvements accepted for TANCHO/CIC Phase II Construction, Contract No. 5852.  (17th AD)
Body
BE IT RESOLVED, that the storm sewer and drinking fountain improvements on TANCHO/CIC Phase II Construction have been completed on 11/11/06  be and are hereby accepted.  
 
Original Contract Sum      $         100,928.16
(Based on Actual Units)      $           87,079.35
Net Change by Change Orders      $             4,592.00 or 4.54%
Liquidated Damages      $                    0.00
Final Contract Amount      $           91,671.35