Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810438-00-53W0257 $91,671.35
Title
Improvements accepted for TANCHO/CIC Phase II Construction, Contract No. 5852. (17th AD)
Body
BE IT RESOLVED, that the storm sewer and drinking fountain improvements on TANCHO/CIC Phase II Construction have been completed on 11/11/06 be and are hereby accepted.
Original Contract Sum $ 100,928.16
(Based on Actual Units) $ 87,079.35
Net Change by Change Orders $ 4,592.00 or 4.54%
Liquidated Damages $ 0.00
Final Contract Amount $ 91,671.35