Title
Improvements accepted for McKee Road @ Stratton Way Intersection Improvement, Contract No. 6357.
Body
BE IT RESOLVED, that the improvements on McKee Road at Stratton Way Intersection Improvement have been completed on 6/05/09 be and are hereby accepted.
Original Contract Sum $ 49,536.60
(Based on Actual Units) $ 52,353.86
Net Change by Change Orders $ 0.00 or 0.00%
Liquidated Damages $ 0.00
Final Contract Amount $ 52,353.86
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810354-00-53W0817 $40,162.16
Acc't. No. CS53-58545-810354-00-53W0817 $12,191.70