Fiscal Note
Breakdown of Costs by Account Number:
CS53-58250-810355-00-53B0568 $253,590.34
ESTM-58270-810381-00-53B0568 $ 98,972.00
ES01-58275-810332-00-53B0568 $452,894.75
EW01-58273-810455-00-53B0568 $103,247.00
Title
Improvements Accepted for N. Thornton, E. Dayton, & N. Dickinson Reconstruction Street Assessment District-2003, Contract No. 5415.
Body
BE IT RESOLVED, that the improvements on N. Thornton, E. Dayton, & N. Dickinson Reconstruction Street Assessment District-2003 have been completed on 3/17/07 and are hereby accepted.
Original Contract Sum $ 88,250.40
(Based on Actual Units) $ 783,624.42
Net Change by Change Orders $ 125,079.75 or 14.2%
Liquidated Damages $ 0.00
Final Contract Amount $ 908,704.17