File #: 45287    Version: 1 Name: Authorizing the Mayor & City Clerk to execute an amended agreement with the WDOT for the construction of City of Madison, Capital City Path Segments 4-6 (Vondron Road to East of IH 39).
Type: Resolution Status: Passed
File created: 11/29/2016 In control: BOARD OF PUBLIC WORKS
On agenda: 1/3/2017 Final action: 1/3/2017
Enactment date: 1/6/2017 Enactment #: RES-17-00013
Title: Authorizing the Mayor and City Clerk to execute an amended agreement with the State of Wisconsin Department of Transportation for the construction of City of Madison, Capital City Path Segments 4-6 (Vondron Road to East of IH 39) (16th AD)
Sponsors: Denise DeMarb
Attachments: 1. Vicinity Map Cap City Path Segments 4-6.pdf
Fiscal Note
The original agreement authorized by RES-14-00877, File ID 35684, encumbered $218,800. The encumbered funds are sufficient for the planned costs that are associated with the initial project phases under this proposed agreement. Additional funding will be required for the City let construction contract scheduled for 2017 construction. The additional required funds are included in the adopted 2017 capital budget in both the major project for:

$365,460: Sufficeint budget authority is authorized within the adopted Engineering-Bicycle and Pedestrian 2017 Capital Budget for the Cap City Trail major project (MUNIS 10143). Funding is provided by GO Borrowing.
$510,000: Sufficient budget authority is authoritzed within the adopted Sewer Utility's 2017 Capital Budget within the Sewer Reconstruction major program (MUNIS 10267). Funding is provided by Revenue Bonds.

Funds will be encumbered when the City let public works contract is awarded in 2017.

Title
Authorizing the Mayor and City Clerk to execute an amended agreement with the State of Wisconsin Department of Transportation for the construction of City of Madison, Capital City Path Segments 4-6 (Vondron Road to East of IH 39) (16th AD)
Body
The proposed project is the construction of approximately 4000’ of a paved multi-use (bike/pedestrian) path that will extend the Capital City Trail From Vondron Road to a location just east of Interstate 39 on the southeast side of Madison. The majority of the path will follow the corridor of the Union Pacific Railroad and will include a new (non-motorized) crossing of the tracks at Wagon Trail. The project will also include the construction of new sanitary sewer. The sanitary sewer will be 100% sponsor funded.

This 3/4 mile segment is a key piece of the remaining 6-mile gap in what will become a continuous 140-mile path across the State. Closing this gap between the Capital City Trail in Madison and the Glacial Drumlin State Trail in the village of Cottage ...