Title
Improvements accepted for Eastmorland Park Drainage Way Assessment District & Eastmorland Bike Path, Contract No. 6170.
Body
BE IT RESOLVED, that the improvements on Eastmorland Park Drainage Way Assessment District & Eastmorland Bike Path have been completed on 10/21/08 be and are hereby accepted.  
 
Original Contract Sum      $         171,57534
(Based on Actual Units)      $         157,584.20
Net Change by Change Orders      $           28,513.90 or 16.61% 
Liquidated Damages      $                   0.00
Final Contract Amount      $         186,098.10
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58240-810375-00-53W0410                 $158,920.38
Acc't. No. ESTM-58270-810382-00-53W0410                  $27,177.72