Title
Improvements accepted for Bedford Street & West Main Street Assessment District - 2007, Contract No. 6003.
Body
BE IT RESOLVED, that the improvements on Bedford Street & West Main Street Assessment District - 2007 have been completed on 12/06/07 be and are hereby accepted.
Original Contract Sum $ 1,084,382.97
(Based on Actual Units) $ 862,474.41
Net Change by Change Orders $ 81,461.80 or 7.51%
Liquidated Damages $ 0.00
Final Contract Amount $ 943,936.21
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53B0878-53TIF028 $286,955.11
Acc't. No. CS53-58270-810355-00-53B0878-53TIF028 $17,607.00
Acc't. No. ESTM-58270-810381-00-53B0878-53TIF028 $79,178.89
Acc't. No. ES01-58275-810332-00-53B0878 $158,357.83
Acc't. No. EW01-58273-810455-00-53B0878 $311,476.38
Acc't. No. CS53-58545-810355-00-53B0878-53TIF028 $90,361.00