Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58280-810376-00-53B0935 $105,665.05
Acc't. No. ESTM-58270-810381-00-53B0935 $7,210.00
Acc't. No. CS53-58250-810354-00-53W0175 $109,685.54
Acc't. No. ESTM-58270-810381-00-53W0104 $14,670.10
Acc't. No. CS53-58545-810354-00-53W0175 $27,277.10
Title
Improvements accepted for Portage Road Sidewalk Assessment District - 2003, Contract No. 5508. (17th AD)
Body
BE IT RESOLVED, that the street, and storm sewer improvements on Portage Road Sidewalk Assessment District - 2003 have been completed on 4/01/05 be and are hereby accepted.
Original Contract Sum $ 130,496.40
(Based on Actual Units) $ 115,020.05
Net Change by Change Orders $ 152,732.74. or 117.03%
Liquidated Damages $ 3,245.00
Final Contract Amount $ 264,507.79