Madison, WI Header
File #: 10701    Version: 1 Name: Change Order No. 1 to Contract No. 6153, Gettle Avenue Lift Station Rehabilitation, to Bachmann Construction Company, Inc. in the amount of $1,449.43 with an additional contract time of 14-days.
Type: Miscellaneous Status: Approved
File created: 5/28/2008 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 6/4/2008
Enactment date: Enactment #:
Title: Change Order No. 1 to Contract No. 6153, Gettle Avenue Lift Station Rehabilitation, to Bachmann Construction Company, Inc. in the amount of $1,449.43 with an additional contract time of 14-days.
Attachments: 1. co 1 - 6153.pdf

Title

Change Order No. 1 to Contract No. 6153, Gettle Avenue Lift Station Rehabilitation, to Bachmann Construction Company, Inc. in the amount of $1,449.43 with an additional contract time of 14-days.

Body

See attached.