Madison, WI Header
File #: 18986    Version: 1 Name: Improvements accepted for Sidewalk & Curb & Gutter, Citywide Installation & Repair - 2009, Contract No. 6295.
Type: Resolution Status: Passed
File created: 6/25/2010 In control: BOARD OF PUBLIC WORKS
On agenda: 7/20/2010 Final action: 7/20/2010
Enactment date: 7/21/2010 Enactment #: RES-10-00655
Title: Improvements accepted for Sidewalk & Curb & Gutter, Citywide Installation & Repair - 2009, Contract No. 6295.
Sponsors: BOARD OF PUBLIC WORKS
Fiscal Note
Breakdown of Costs by Account Number:
 
Acc't. No. CS53-54473-810376-00-53W0707        $122,476.90
Acc't. No. CS53-58280-810376-00-53W0707          $36,792.29
Acc't. No. CS53-54472-810358-00-53W0707            $2,291.40
Acc't. No. CS53-58250-810360-00-53W0707            $3,780.00
Title
Improvements accepted for Sidewalk & Curb & Gutter, Citywide Installation & Repair - 2009, Contract No. 6295.
Body
BE IT RESOLVED, that the improvements on Sidewalk & Curb & Gutter, Citywide Installation & Repair - 2009 have been completed on 11/20/09 be and are hereby accepted.  
 
Original Contract Sum      $          395,015.00
(Based on Actual Units)      $          161,560.59
Net Change by Change Orders      $             3,780.00 or 0.96%
Liquidated Damages      $                   0.00
Final Contract Amount      $         165,340.59